13012 Dykstra 62

From NavykI
Revision as of 07:57, 20 September 2013 by 192.168.11.27 (talk) (Fresh water)

Jump to: navigation, search

General

Description

Contacts

  • client: Dick Alewijnse (NL) - DA is contactperson for all questions regarding systems
  • project manager: Robin ten Hoope (NL) - RtH also drew up the interior since GDNP did not have time for it
  • contact person GDNP: Erik Wassen (NL)

Classification

Scope

Drawing list

Time schedule

Trivia

  • carbon mast costs about 250K which is more expensive than the interior (and the interior is more expensive than the aluminum construction)
  • sistership 'Windhunter III' is build by Aluboot (Henk Borneman) and owned by Johan Mast
  • ballast system with dumphatches is developed by Heine Deelstra from Gaastmeer Design, in cooperation with K&M Yachtbuilders

Questions

To do

Minutes of Meeting

06-09-2013

Dick Alewijnse, Erik Wassen, Robin ten Hoope

1 CONSTRUCTION

  • A Keelconstruction/guides/stability trembling / nose through deck / with/without shell bulb
    • One side plastic material on trunk, anodized guide part on keel
    • Keel configuration and construction detailed and delivered by Dykstra
    • Forward part of keel as high as possible, partially penetrating through deck
    • Up/down movement speed 1m/min
    • Cylinder pushes keel in lower position tight against shell, max. pressure to be definded (EW)
    • In upper position the keel enters in the wedge shaped trunk which will secure the keel
    • Bulb of casted lead (in mould)
    • Internal a galvanized frame with threaded ends, mounted with galvanized nuts
    • Between bulb and keel an isolating part which separates lead from aluminum
    • Also the penetration of the threaded ends need to be isolated
  • B Alustar
    • NO ALUSTAR. Advantages do not outweigh the disadvantages of a yacht of this size.
  • C Final shell stingers
    • Stringers are OK as drawn by Navyk
  • D Miscelaneous remarks/modifications of drawings
    • Stairs in interior in way of trunk gearbox is not properly aligned, situation to be modified (RtH)
    • When stairs is OK then optimize drive line by moving gearbox aftward, decrease distance engine-gearbox, if necessary make a small bulb in shell for gearbox (RtH / EW)
    • Detail garage of entrance hatch in combination with scupper pipes (RtH)
    • Define softpatch size and position, generator must be removable with engine in place (RtH)
    • Add double plates and deck reinforcements (EW)
    • What impact has relocating the PS ER bhd, how will be detailing of bathroom, how much free space requires the Turbo of the Steyr? (RtH)
    • Indicate cockpit recesses, make proposal (RtH)
    • Add additional pillars in way of F19 (mainsheet track) (RtH)
  • E Penetrations/standpipes
    • Determine position of standpipes for in and outlet, centralize as much as possible (RtH)
  • F Dishwasher – modify recess
    • Give Navyk new dimensions and position so this can be processed (RtH/EW)
  • G Windows in aftside deckhouse
    • To be determined in combination with interior and exterior sideview, make proposal for Dykstra approval (RtH)
  • H Hatch sill entrance
    • Not discussed, make proposal for Dykstra approval (RtH)
  • I Porthole positions
    • Pass new postions to Navyk so it can be updated in the construction plan (RtH)
  • J Align PS ER bhd with cockpit seat
    • What impact has relocating the PS ER bhd, how will be detailing of bathroom, how much free space requires the Turbo of the Steyr? (RtH)
  • K WT doors relocated in BHD
    • Determine new door type and position and inform Navyk (Rt)
  • L Tanks ballast, fresh and grey. Discuss function and execution
    • Situation unchanged
  • M Motor position in relation with twindisc
    • Twin disc is no option because of angle which requires too many couplings

2 DECK PLAN

  • A Layout related to sailplan and sheeting, check
    • Conform latest deckplan. Staysail to be drawn (EW, done 06-09-2013)
  • B Sheeting/halyard angles to winches, check
    • determine angles and heights for wich feeding (EW)
  • C Complete equipment list
    • check execution and delivery for hardware quotes (EW)
    • strategic locations for fixed padeyes, upstands and footblocks (EW)
    • add 2 deflection points for kite/code sheet to winch (EW)
  • D Skylight salon, general details, constr. etc. (EW)
    • skylight with dorade forward of F13 and extend glass 200m aft (RtH/EW)
  • E Construction deckhouse, construction aluminum with wood, integrated windows, location additional pillars related to entrance, etc
    • Dykstra will give principal details as a guide for the construction (EW)
  • G Possibility of second travellercar on forward rail
    • Extend foundation in deck for optional rail extension (EW)
  • H Move fairlead to bollard
    • Dykstra will move this (EW)
  • I Entrance hatch principles
    • Dykstra will give principle (EW)

3 SAIL PLAN

  • A Raised forestay still possible with mast of Hall-spars?
    • will influence current offer of Hallspars. New offer required based upon new built profile
  • B Sail area to be checked, behaviour under different conditions
    • Dykstra will make a new sailplan with all data given for price offer mast and hardware (EW)

4 INTERIOR

  • A Interior drawings handed over to Dykstra for their approval
    • drawings are handed over

5 MISCELANEOUS

  • A What else Dykstra will do / finish?
  • B Bowsprit
    • Dykstra will set up bowsprit geometry with adjustable water stay (EW)
  • C Fender storage in fore peak
    • Alewijnse likes to store fenders in forepeak between hull and chainlocker, is this possible?
    • Yes, see mail 06-09-2013 EW
  • D Mainsheeting details
    • details and geometry of system of run through deckhouse (EW)
  • E No pulpit at bow
    • drawings will be updated (EW)
  • F weight estimation systems
    • systems and positions arranged for weight calculation (RtH)

10 General arrangement

20 Naval architecture

40 Construction

  • frames will be all CNC
  • bulb profiles changed into FB60x6
  • deckhouse will be aluminium (by phone with Dykstra)
  • bulkhead stiffening will be: vertical T50x50x5 and horizontal FB50x5 (wait for answer)
  • shell division and as well other plate division will be made by Navyk (wait until a yard is chosen) (by phone with Dykstra)
  • chain locker for anchor will be from aluminium 5mm (by phone with Dykstra)
  • bow thruster construction will be finished by Navyk (by phone with Dykstra)
  • plate under stairs iwo cockpit entrance will be as in the construction drawing (by phone with Dykstra)Changed

Liftkeel

50 Outfitting

60 Systems

General

  • overboards - all above WL
  • overboards - combine as much as possible
  • valves - reduce number of valves where possible
  • drafting
    • draw at scale 1:1
    • scale in titleblock is 'NA' (not applicable)
    • uniform use of symbols
    • uniform size of symbols
    • all tables grouped vertical in right side of drawing
    • all on A2 format?
    • use new titleblock / notes / table
    • don't add unnecessary knucles in lines
    • in the near future we should standarize symbols and draw the diagrams on a grid of 10x10
    • use ball valve symbol instead of globe valve symbol
    • use E for electric operated valves
  • collect supplier data for each appliance (in the project folder there is not any documentation)

Ballastsystem Windhunter

    • breather pipe must have sufficient diameter, Windhunter has Ø50 which is considered too small, they advice Ø80
    • breatherpipes go to grills in aftside doghouse
    • when breatherpipes overflow you know the tanks are full
    • Goiot hatches operation lines are lead to the cockpit and have a 2:1 tackle
    • Goiot hatcehs have a lever
    • double bottom is used as cross over, K&M is not satisfied with (hard to make watertight, no inspection possible) and prefers 2 or 3 large diameter pipes
    • Goiot deckhatch rectangular, for example 300x500 or 250x400, plexiglas replaced by aluminum panel
    • advantage of using standard deckhatch is that spareparts like gaskets can be easily found and replaced
    • Windhunter uses only ballastwater, we use a combination with grey water which gives smells so the breather pipe should be a closed ring?

Bilge

  • manifold in galley (against trunk ER?), all manual valves well accessible
  • draw breathers always in upper end of line
  • seperate cross over from fill/suction line (saves 1 BIG manifold)
  • calculate fill up/empty time for wing tank (verify cross sections of breather + cross over)

Fresh water

  • note: wingtanks are not intended for storage because they heat up due to blue hull FW wing tanks will be used for storage, filled from bottom tanks
  • reduce number of valves
  • toilets possibly come with double connections for FW / seawater, then no valve required, check this out (possible supplier is Raritan or Tecma) Toilets mentioned doesn't have separate connections
  • pumps, hydrofor, etc - to be removable: valves fore and aft
  • add taps at low points
  • reduce overboards by combining pipes
  • use colors for hot (don't use 'warm') and cold water
  • disconnect sea water tap galley from FW system
  • calculate required time to fill up wingtanks with hydrophor
  • breatherpipes wingtanks of sufficient diameter (calculate time required to empty/fill one tank?)
  • breatherpipes wingtanks to keeltrunk?
  • connect crossovers to bottom of wingtanks
  • connect fill lines to sides of bottomtanks
  • LS of HL as in bilge diagram? Only LS will be used

questions / remarks SH

  • Robin - bottom tanks - did we discuss about increasing the size or moving? Tank volumes shall not be increased
  • cross over and breather section to be calculated (how much time it takes to move the water from PS to SB)
  • fill - why via wingtanks? wingtanks should not be used for storage so fill should go directly to bottomtanks? DONE
  • wing tanks - why drain? Now they are used also for storage, so drain is required
  • wing tanks - why spare connection on top? Spare connection from wing tanks removed
  • wing tanks - avoid that water drains through breather line
  • wing tanks - extend fill line to near bottom to reduce noise?
  • bottom tanks - why a valve in breather line? Removed
  • watermaker - connect directly to bottom tanks only? Yes, wing tanks shall be filled from bottom tanks with the hydrophor
  • cross over - always filled with water
  • hot water to laundry machine? Laundry machine does not need hot water, only the dishwasher

Sea water

  • galley - own faucet, no connection to FW faucet

Black water

  • breather aft in transom, forward in mast?

Fuel

  • pump does not require electric valves fore and aft
  • Fuel transfer system has 20 l/min and 30 l/min flow rate for the pumps and 5 l/min for duplex filter. Should we put a bigger filter?

Electric

  • generator - Northern Lights? Wisperpower company is running into troubles?

Propulsion

  • Steyr 4 or 6 cylinder
  • check out if 26" prop can be combined with Twindisc gearbox, because of space issue, ER trunk might require modification, together with interior engine/shaft angles can be modified, keep 30% tipdistance for propellor, longitudinal position can be modified
  • propellor
    • Flexofold 26" (optional 25" or 28", pending on engine and gearbox combination, issue is behaviour of sailing reverse)
  • drawing of Twindisc is in e-mail of 22-07-2013

70 Interior

80 Paint and insulation

90 Safety