  • Goal is to reduce costs of labour and/or material with € 4.000 minimum
  • FEM calculations for the following:
    • hulls
  1. existing hull in 3mm
  2. existing hull in 3mm with deck 2mm
  3. existing hull in 3mm with reduced number of watertight bulkheads and with PUR foam
  4. circular hull in 3mm
  5. circular hull in 3mm with reduced number of watertight bulkheads and with PUR foam
    • platform
  1. beams with 3mm wall thickness
  2. reduced number of beams with 3mm wall thickness
    • portal
      • aluminum pillars, steel beam
      • existing aluminum constructed beam bends 11mm after 'placing steel (longitudinal?!) beam'
      • note:
        • connection beam/pillar must be internal since wooden construction walls connect direct to portal
        • drain hose passes through beam/pillar (see pictures in 13006)
  • for circular hull:
    • maintain platform height
    • vary draft
  • CE-conformity
  • construction detail existing deck: WT bhd has flange on top which is used for welding deck seam