14023 Floating 44

From NavykI
Revision as of 10:15, 26 January 2015 by 31.160.12.62 (talk)

(diff) ← Older revision | Latest revision (diff) | Newer revision → (diff)
Jump to: navigation, search
  • Goal is to reduce costs of labour and/or material with € 4.000 minimum
  • FEM calculations for the following:
    • hulls
  1. existing hull in 3mm
  2. existing hull in 3mm with deck 2mm
  3. existing hull in 3mm with reduced number of watertight bulkheads and with PUR foam
  4. circular hull in 3mm
  5. circular hull in 3mm with reduced number of watertight bulkheads and with PUR foam
  6. for all hulls the size of the longitudinal beam to be reduced from 150x60x4 to 80x40x3/4
    • platform
  1. beams with 3mm wall thickness
  2. reduced number of beams with 3mm wall thickness
    • portal
      • aluminum pillars, steel beam
      • existing aluminum constructed beam bends 11mm after 'placing steel (longitudinal?!) beam'
      • note:
        • connection beam/pillar must be internal since wooden construction walls connect direct to portal
        • drain hose passes through beam/pillar (see pictures in 13006)
  • for circular hull:
    • maintain platform height
    • vary draft
  • CE-conformity
  • construction detail existing deck: WT bhd has flange on top which is used for welding deck seam
  • planning - end of May delivery of calculations and drawings
  • direct contact with constructor for questions regarding material/prices:
    • Martens Constructie-Lasbedrijf
    • Voordeldonk 73a
    • 5721HL Asten
    • Tel +31 493 693 499
    • Mob +31 620 416 378